Multiple Choice
TIME: 1-hour |
| Instructions |
1. All 75 questions should be attempted.
2. 5 of the 75 questions are under trial and will not contribute to your overall score. There is no indication of which questions are under trial.
3. All answers are to be marked on the answer sheet provided.
4. Please use a pencil and NOT ink to mark your answers on the answer sheet provided. There is only one correct answer per question.
5. You have 1 hour for this paper.
6. You must get 35 or more correct answers to pass. |
1.
Which aspect of project
performance must be managed to ensure the project's products are fit for
purpose?
A. Benefits
B. Quality
C. Risk
D. Scope
2.
Which principle helps to define
what should be included and what should be excluded from a project?
A. Defined
roles and responsibilities
B. Focus on
products
C. Manage by
stages
D. Continued
business justification
3.
Which project characteristic suggests
that projects should have a defined start and a defined end?
A. Change
B. Temporary
C. Cross-functional
D. Risk
4.
Identify the missing words in the following
sentence.
A project is [ ? ] organization that is created
for the purpose of delivering business products.
A. a
corporate
B. a
temporary
C. an
external
D. a
technical
5.
Which is one of the four integrated elements within
PRINCE2?
A. Activities
B. Processes
C. Products
D. Techniques
6.
Which is a benefit of using PRINCE2?
A. It is a
method specifically designed for technical projects
B. It
provides for the efficient and economic use of management time
C. It
includes many of the proven planning techniques, such as critical path analysis
D. It can be
used to manage both projects and programmes
7.
Which is assumed to be a
customer's responsibility in the PRINCE2 customer/supplier environment?
A. Specifying
the desired result
B. Providing
the resources and skills to deliver the desired result
C. Ensuring
the technical integrity of a project
D. Developing
a project's products
8.
What is documented in the Benefits Review Plan?
A. Risks to
the realization of the expected benefits
B. Activities
to measure the expected benefits
C. Business
justification for undertaking the project
D. Overall
costs and timescales of the project
9.
Which theme provides the justification for the
project?
A. Quality
B. Plans
C. Progress
D. Business
Case
10. Which
product should be used to record a project's expected dis-benefits?
A. Project
Product Description
B. Business
Case
C. Project
Plan
D. Risk
Register
11. Which
role could the Project Manager also perform?
A. Executive
B. Senior
Supplier
C. Project
Assurance
D. Team
Manager
12. Which
statement about stakeholder interests is FALSE?
A.
The Project Board should have
representation from each of the business, user and supplier interests
B. The term
'customer' is usually interpreted as a collective term for the business and
user interests
C. The
Senior Supplier(s) will represent the interests of those who will operate the
project's outputs.
D. The
Executive will represent those individuals or groups who have an interest in
the project's finances.
13. Who are
considered as the stakeholders in a project?
A. Only
those benefitting from the project
B. Everyone
in the corporate organization
C. Everyone
involved in or affected by the project
D. Only those
in the customer organization
14.
What can be done to control the
size of the Project Board on a project that involves multiple users and
suppliers?
A. Create a
separate Project Board to manage the supplier elements of the project
B. Create
multiple smaller Project Boards during the process of Starting up a Project,
one for each of the project's stages.
C. Create
user and supplier groups
D. Appoint
corporate quality assurance to perform the Project Assurance role for all
members of the Project Board
15. Which
role is part of the Project Board?
A. Corporate
or programme management
B. Risk
owner
C. Project
Manager
D. Senior
Supplier
16. Which is
a purpose of the Organization theme?
A. To
determine the necessary project resources
B. To
establish governance for the project
C. To
capture the stakeholders' project acceptance criteria
D. To assess
the level of uncertainty that needs controlling
17. Who
should a project assurance role report to?
A. Every
member of the project management team
B. Only the
Executive of the Project Board
C. The
Project Board member for the area of interest
D. The
Project Manager for the project
18. Which is
an objective of the quality review technique?
A. To
identify a product's quality criteria
B. To
provide assurance that the project is being conducted properly
C. To assess
that a product conforms to set criteria
D. To ensure
that staff are properly trained in the quality methods
19. Which is
a recommended quality review team role?
A. Project
Manager
B. Assurance
C. Chair
D. Producer
20. Which
statements about customer's quality expectations are CORRECT?
1. They form
a specific and precise list of measurable criteria
2. They
define the approval method for the products
3. They are
often expressed in broad terms
4. They are
provided by the Senior User
A. 1 and 2
B. 2 and 3
C. 3 and 4
D. 1 and 4
21. Which is
a purpose of a Project Product Description?
A. To
document the quality expectations of the customer
B. To
outline the quality assurance methods to be used by the project
C. To ensure
that Project Assurance responsibilities are defined for monitoring product
delivery
D. To
provide details of what information will be produced for stakeholders and at
what frequency it will be required
22. Which is
a purpose of the Quality theme?
A. To
establish how the project will ensure that all products created meet their
requirements
B. To
establish quality assurance to maintain the quality management system
C. To
identify all the products of the project to ensure the scope has been
adequately defined
D. To
determine the communication needs of the organization's quality assurance
function
23. Identify
the missing word(s) in the following sentence.
Quality assurance provides assurance to the [ ?
] that the project is being conducted appropriately whilst Project Assurance
provides the same assurance to all the project's stakeholders.
A. Project
Manager
B. Executive
C. corporate
or programme management organization
D. Supplier
groups
24. Which is
part of quality control?
A. Documenting
the project's acceptance criteria in the Project Product Description
B. Defining
the quality responsibilities of those involved in the production of the
products
C. Producing
quality records to show that the planned quality activities have been carried
out
D. Maintaining
the corporate organization's quality management system
25. Which
product identifies the management stages and timescales of a project?
A. Project
Brief
B. Project
Product Description
C. Project
Plan
D. Initiation
Stage Plan
26. Which is
a purpose of an Exception Plan?
A. To show
the reason for the tolerance deviation from a Stage Plan or Project Plan
B. To reduce
the number of exception assessments, by agreeing a budget to cover the costs of
any requests for change
C. To
identify the actions required to recover from the effect of a tolerance
deviation
D. To define
the changes which are within the scope of the change budget
27. What are
the three levels of plan recommended by PRINCE2?
A. Benefits
Review Plan, Exception Plan, Project Plan
B. Benefits
Review Plan, Project Plan, Stage Plan
C. Exception
Plan, Project Plan, Stage Plan
D. Project
Plan, Stage Plan, Team Plan
28. Which
product-based planning activity is undertaken for the Project Plan only?
A. Create
the product flow diagram
B. Write the
Product Descriptions
C. Create
the product breakdown structure
D. Write the
Project Product Description
29. Identify
the missing words in the following sentence.
The first
task of [ ? ] is writing the Project Product
Description.
A. product-based
planning
B. the
initiation stage
C. the
PRINCE2 approach to plans
D. the issue
and change control procedure
30. What is
performed as part of the recommended risk management procedure?
A. A budget
to investigate issues is allocated
B. Risk
management practices are reviewed to ensure that they are performed effectively
C. Information
about risks to the projects is sent to project stakeholders
D. Conflicts
between the project and the programme board are
resolved
31. Which
statement describes the responsibilities of a risk actionee?
A. To
identifying risks to the project that might occur in their department
B. To own
and authorize the use of the risk budget to fund risk responses
C. To
manage, monitor and control of all aspects of an assigned risk
D. To carry
out a risk response action to respond to a particular risk
32. What is
risk impact?
A. The
timeframe within which the risk might occur
B. The
trigger that occurred giving rise to the risk
C. The
effect of the risk on the delivery of project objectives
D. The
probability of the risk occurring in a given project situation
33. What is a
risk effect?
A. The
uncertainty expressed as a negative or favourable
occurrence
B. The issue
which is affecting the project and has resulted in a risk
C. The
impact(s) on the project objectives should the threat or opportunity occur
D. The
change in the status of a risk in response to actions taken to control it
34. Which is
a purpose of a Risk Register?
A. To
capture risks that may occur during the project
B. To record
how risk management activities will be undertaken on the project
C. To record
the risk tolerance for the project
D. To
capture issues which are impacting on the delivery of the project objectives
35. "Which
statements about risk are CORRECT?
1. A risk is defined as an uncertain event that, should it occur, will have
an effect on the achievement of objectives
2. An
opportunity is a risk that could have a positive impact on the achievement of
objectives
3. An
off-specification is a risk that a product will fail to meet its quality
criteria
4. A threat
is a negative consequence that will occur from carrying out the project"
A. 1 and 2
B. 2 and 3
C. 3 and 4
D. 1 and 4
36. Which
risk response type is appropriate to respond to an opportunity?
A. Accept
B. Fallback
C. Exploit
D. Transfer
37. What may
be funded from a risk budget?
A. Corrections
required due to off-specifications
B. Impact
analysis of requests for change
C. Implementation
of a fallback plan
D. Preparation
of the Risk Management Strategy
38. Which is
a purpose of the Risk theme?
A.
To establish a procedure to
ensure every change is agreed by the relevant authority before it takes place
B. To
establish a cost-effective procedure to identify, assess and control
uncertainty
C. To
establish mechanisms to control any unacceptable deviations from plan
D.
To establish mechanisms to manage
risks at the corporate or programme level of an
organization
39. What is
an off-specification?
A. A new
requirement
B. A quality
tolerance
C. A type of
issue
D. A major
risk
40. Which is
a typical core activity within configuration management?
A. Issue
management
B. Quality
inspection
C. Identification
D. Preparation
41. Which
product is used to obtain formal advice from the Project Board?
A. Checkpoint
Report
B. Issue
Report
C. Work
Package
D. Follow-on
action recommendations
42. Which
statement about the Change theme is INCORRECT?
A. Change
control should prevent any changes to baselined
products
B. Baselined products require configuration
management to ensure control
C. A project
can fail without a successful change control procedure
D. Changes
should be assessed against baselined products
43. Which
describes a use of a Configuration Item Record?
A. To define
the identification scheme to be applied to the project
B. To
identify the techniques and procedures required within the Work Package
C. To record
the change in a product's status
D. To record
the reporting requirements for the Work Package
44. Which
should be funded from a change budget?
A. The
Starting up a Project process
B. A
fallback plan
C. An agreed
change to the scope of a project
D. A change
to a plan, within allocated tolerances, due to poor estimating
45. Who does
the Team Manager report to and take direction from?
A. Project
Board
B. Project
Assurance
C. Project
Manager
D. Project
Support
46. Which is
a difference between management and technical stages?
A. Management
stages require planning; technical stages do NOT require planning
B. Technical
stages can overlap; management stages CANNOT overlap
C. Management
stages deliver products; technical stages do NOT deliver products
D. Technical
stages require resources; management stages do NOT require resources
47.
Which product is used to pass
responsibility for the delivery of a product to a Team Manager or team member?
A. Stage
Plan
B. Product
Description
C. Checkpoint
Report
D. Work
Package
48. Whose
approval is needed to replace a Stage Plan with an Exception Plan?
A. Corporate
or programme management
B. Project
Board
C. Project
Manager
D. Team
Manager
49. How many
management stages should a PRINCE2 project consist of?
A. Start up stage, initiation stage and at
least one other management stage to cover the remainder of the project
B. Start up stage, at least one other
management stage to cover the remainder of the project and a closing stage
C. Initiation
stage and at least one other management stage to cover the remainder of the
project
D. Start up stage, initiation stage and a
closing stage
50. Which is
NOT a purpose of the Progress theme?
A. To
monitor and compare actual achievement against those planned
B. To define
the means of delivering products
C. To
control any unacceptable deviation
D. To
provide a forecast for the project objectives and the project's continued
viability
51. Where
should the Project Manager record an issue that is being managed informally?
A. Issue
Register
B. Daily Log
C. Risk
Register
D. Lessons
Log
52. Which is
a purpose of an End Stage Report?
A. To allow
the Project Manager to decide whether the project should continue
B. To inform
the Project Manager about stage progress
C. To allow
the Project Board to decide whether to authorize the next stage
D. To
recommend project closure to the Project Board
53. Which is
an objective of the Starting up a Project process?
A. To
approve the initiation stage
B. To select
the project mandate
C. To define
the project Quality Management Strategy
D. To
appoint the project management team
54.
Which process ensures that key
roles and responsibilities are allocated before a decision is made to initiate
a project?
A. Managing
Product Delivery
B. Initiating
a Project
C. Managing
a Stage Boundary
D. Starting
up a Project
55. Why is a
Project Brief produced?
A. To act as
a trigger for the Starting up a Project process
B. To record
the strategies and management controls to be used by a project
C. To provide
a full and firm foundation for the initiation of a project
D. To be
used by the Project Board as a basis for reviewing the progress of a project
56.
During the Starting up a Project
process, what should be done to reduce the number of issues and exceptions in
later stages?
A. Evaluate
possible methods of delivering the project
B. Appoint
the Team Managers
C. Ensure
the requirements are captured clearly
D. Produce
the initiation Stage Plan
57. What
process is used by the Project Board to respond to an Exception Report?
A. Controlling
a Stage
B. Managing
a Stage Boundary
C. Managing
Product Delivery
D. Directing
a Project
58. Which is
a key decision made during the Directing a Project process?
A. Select
and appoint the Project Executive
B. Approve
the Project Manager role description
C. Confirm
that the Benefits Review Plan addresses all expected benefits
D. Approve
the proposed Project Mandate
59. Which is
an objective of the Directing a Project process?
A. To revise
the Project Mandate in response to any events external to the project
B. To provide
an interface between project and corporate or programme
management
C. To
establish a solid foundation for commencing the Starting up a Project process
D. To define
the arrangements for implementing project governance arrangements
60.
What process provides the
information required to decide whether to authorize the delivery of a project?
A. Directing
a Project
B. Initiating
a Project
C. Managing
Product Delivery
D. Starting
up a Project
61. Which
statements about the Project Initiation Documentation are CORRECT?
1. It is used to ensure that a sound basis exists before the Project Board
authorizes a project
2. It should
be updated at the end of each stage to reflect the current status of a project
3. It is
assembled in the Starting up a Project process
4. It
describes how the principles will be tailored for the project
A. 1 and 2
B. 2 and 3
C. 3 and 4
D. 1 and 4
62. Which
process is used to define how baselines will be established and controlled?
A. Controlling
a Stage
B. Directing
a Project
C. Initiating
a Project
D. Starting
up a Project
63.
Which document should specify how
the Project Board will approve the management products created during the
Initiating a Project process?
A. Project
Plan
B. Initiation
Stage Plan
C. Quality
Management Strategy
D. Project
Initiation Documentation
64.
Which process is triggered
towards the end of the final stage when all the assigned work has been
completed?
A. Managing
a Stage Boundary
B. Managing
Product Delivery
C. Closing a
Project
D. Controlling
a Stage
65. Which is
a purpose of the Controlling a Stage process?
A. To assign
work to be done and take corrective action to ensure that the stage remains
within tolerance
B. To
provide a fixed reference point at which acceptance for the project product is
confirmed
C. To enable
the Project Board to be provided with sufficient information to authorize the
next stage
D. To enable
the organization to understand the work that needs to be done to deliver the
project's products
66. Identify
the missing words in the following sentence.
An objective of the [ ? ] process is to ensure
that risks and issues are kept under control through active management.
A. Managing
a Stage Boundary
B. Directing
a Project
C. Controlling
a Stage
D. Managing
Product Delivery
67. When are
tolerances for a Work Package agreed?
A. When
accepting a Work Package
B. When work
on each product within the Work Package begins
C. When all
products have been developed and approved
D. When the
Stage Plan is authorized by the Project Board
68. Which two
roles are linked by the Managing Product Delivery process?
A. Corporate
or programme management and Project Board
B. Project
Board and Project Manager
C. Project
Manager and Team Manager
D. Team
Manager and external supplier
69.
Which process aims to ensure
accurate progress information is provided to the Project Manager?
A. Starting
up a Project
B. Managing
a Stage Boundary
C. Managing
Product Delivery
D. Directing
a Project
70.
Which plan is created, and
submitted for approval, during the Managing a Stage Boundary process?
A. Team Plan
B. Stage Plan
C. Benefits
Review Plan
D. Project
Plan
71.
Which process provides
information for the Project Board to review a completed stage and confirm
continued business justification?
A. Controlling
a Stage
B. Closing a
Project
C. Directing
a Project
D. Managing
a Stage Boundary
72.
During the Managing a Stage
Boundary process, if external factors are identified that may affect the
business justification for a project, which product should be updated?
A. Business
Case
B. Project
Brief
C. End
Project Report
D. Highlight
Report
73. Which
statements about the Closing a Project process are
CORRECT?
1. It
receives the completed Work Packages for the final stage
2. It
reviews whether the original objectives have been achieved.
3. It
confirms that the project product has been accepted
4. It
includes the production of the Benefits Review Plan
A. 1 and 2
B. 2 and 3
C. 3 and 4
D. 1 and 4
74. When are
project closure activities planned?
A. During
the initiation stage
B. When the
Stage Plan for the final management stage is produced
C. As the
first activity in the Closing a Project process
D. In the
last Work Package allocated to a Team Manager
75. Which is
an objective of the Closing a Project process?
A. To
prepare the plan for the next stage
B. To assess
any benefits that have already been realized
C. To
produce a Benefits Review Plan to identify what benefits are expected
D. To check
that all benefits are realized before closing a project